Home Quizzes Quiz Detail
Practice Quiz

ACG Certified Commissioning Authority (CxA) Practice Exam

10 questions 5.0 rating Mobile friendly
$69.00

Unlock the full practice quiz

Get complete access to the questions, explanations and printable quiz resources.

Full access: unlock all quiz questions and explanations.
Printable review: access the full quiz PDF with correct answers after purchase.

About this Exam

Prepare with the ACG Certified Commissioning Authority (CxA) Practice Exam practice quiz. This question bank includes 10 questions covering stands, construction, mechanical, design, and commissioning. Use it to review important concepts, identify knowledge gaps, and build confidence for the related exam, course, or assessment.

Sample Questions

Question 1
DO stands for?
Direct output
Data output
Digital optical output
Digital output
Explanation:
Digital output is the signal type used for binary, on/off control in many controllers. It represents a channel that the system uses to drive field devices like relays, contactors, or actuators, switching between a high and a low state rather than producing a continuously varying value. This distinction—digital versus analog—helps technicians understand what kind of signal to expect from a controller and how to interface with it. The term digital output specifically communicates that the output is a discrete, binary signal intended to actuate a device, not a variable or data stream. The other terms aren’t standard in this context: direct output isn’t a common designation, data output is too generic and could refer to any data channel, and digital optical output would imply an optical signaling method, which isn’t the usual meaning of DO in control schematics.
Question 2
Which item does not typically occur during turnover/handover?
Documentation is handed over
O&M manuals provided
System checkout is performed
Sasol procedures such as LOTO and confined space
Explanation:
Turnover/handover is about transferring the finished asset with the information the new operator needs to run and maintain it. The items that fit this moment are delivering the documentation and providing the operating materials. Documentation being handed over ensures the owner has the complete records, while providing O&M manuals equips the new team to operate and maintain the system. A system checkout, on the other hand, is a commissioning activity that is completed to prove the system works to specification, and its results are typically finalized before turnover. The owner receives evidence of performance rather than re-doing the checks during handover. Sasol procedures such as LOTO and confined-space are safety practices used during the work on site—during construction and commissioning—to protect workers. They belong to the safety program and work execution phase, not to the asset handover content. That’s why these safety procedures do not typically occur as part of the turnover package.
Question 3
Which two phases are identified for the Retro/Re-Commissioning process?
Planning and Implementation
Planning and Execution
Design and Construction
Evaluation and Commissioning
Explanation:
Retro/Re-Commissioning is treated as a two-phase effort focused on existing buildings: planning and implementation. In the planning phase, you scope the RCx project, gather and analyze energy data, establish a baseline, identify and prioritize potential retrofits, and set objectives, metrics, and a plan for measuring success. The implementation phase then covers selecting and installing the recommended measures, adjusting controls, training operators, and verifying that the expected energy savings and improved performance are realized. This structure keeps the work organized: first decide what to change and how you’ll measure it, then carry out the changes and confirm the results. Other pairings shift focus toward new construction design/construction or post-occupancy verification in contexts that aren’t the standard RCx two-phase approach.
Question 4
Which acronym stands for the 'Resolution tracking form'?
RTF
Resolution tracking form
System verification check
Test and balance engineer
Explanation:
Acronyms are created by taking the first letter of each word in a multi-word term. For “Resolution tracking form,” the initial letters are R, T, and F, forming the acronym RTF. This shorthand is used in documentation to refer to the form quickly without spelling out all three words. The option that corresponds to this acronym is the correct one, while the other choice presents the full phrase or points to a different concept and isn’t the abbreviation for that term.
Question 5
New construction commissioning costs as a percentage of total mechanical system construction cost range from which of the following?
1 to 2%
3 to 4%
2 to 3%
4 to 5%
Explanation:
Planning and conducting new construction commissioning is a structured effort that validates that mechanical systems meet design intent, operate correctly, and perform as expected. The cost covers developing the commissioning plan, reviewing design and submittals, coordinating and witnessing tests, on-site verification, documentation, and training staff. On most projects, this work amounts to about two to three percent of the total mechanical system construction cost. This range represents a thorough level of verification without overburdening the project budget. If the project is unusually simple, the percentage can be lower; if it’s highly complex or requires extensive integration and performance guarantees, the cost can climb toward four percent or more, but the standard expectation for typical new construction sits at two to three percent.

Ready to test your knowledge?

Buy Now to Access

Additional Information

ACG Certified Commissioning Authority (CxA) Practice Exam

This practice set contains 10 questions from the matching question bank and focuses on stands, construction, mechanical, design, and commissioning. Work through each question carefully, review the provided solutions, and revisit topics that need more study before your next attempt.

This is an independent study resource intended for practice and review; it is not an official examination or an endorsement by any organization named in the title.

Frequently Asked Questions

This quiz contains a total of 10 practice questions carefully selected to test your knowledge on this subject.
Yes, you will have exactly 0 minutes to complete the exam. A countdown timer will be visible once you start.
Yes, you can retake this practice test as many times as you need. The questions and options may be randomized on subsequent attempts to ensure comprehensive learning.

Reviews

5.0

Based on 0 reviews

Leave a Review

No reviews yet. Be the first to review!